As you know (or if you don't you do now) the Municipal park is undergoing renovations funded by the National Lottery Heritage fund. Further info (plans etc) will be posted here as soon as I get them and I am also going to be posting photographs as the work progresses from time to time (I have been granted permission from the council and site managers as well as the Whistledown hotel to access the site and take pictures)

To start with just a couple of snaps from outside showing some of the damaged tree's being removed. (they will all be replaced and a heritage garden specialist is overseeing the replanting etc)


Attachments:
p2.jpg
p2.jpg [ 59.11 KiB | Viewed 2110 times ]
p1.jpg
p1.jpg [ 51.78 KiB | Viewed 2110 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Fri Feb 09, 2018 10:04 am 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Press Release 22nd January 2018


Warrenpoint Municipal Park has now closed prior to the commencement of restoration work to restore and upgrade facilities.

Quote:
Newry, Mourne and Down District Council successfully received funding of £850,000 from the Heritage Lottery Fund’s Parks for People Programme towards the project. With the recent appointment of the Main Contractor Quinn Automatic Ltd, the proposed project of restoration and regeneration will commence within the next couple of weeks with completion in summer 2018.

Newry, Mourne and Down District Council Chairperson, Councillor Roisin Mulgrew said, “I am delighted that Newry, Mourne and Down District Council can now begin works in the historic Warrenpoint Municipal Park. It is listed on the Register of Parks and Gardens of Special Historic Interest Northern Ireland and this important restoration project will preserve the heritage of this beautiful park for future generations to enjoy.”

The project will safeguard the park’s many historic features: the listed bandstand, which is one of the finest remaining examples in Northern Ireland, will be carefully restored; the Pavilion Building, which dates from the 1930s, will be reestablished as an Interpretive Centre; the original planting will be reinstated and pathways will be resurfaced. A new coherent range of street furniture will also be installed as part of the works to include lighting, seats, bins, a park shelter, park notices and signage.

Cllr Mulgrew continued, “The children’s play area will be upgraded with the installation of new play equipment and play surfaces and the tennis courts will be upgraded to an informal games area with specialist surfacing for tennis and other games. An associated development programme of activities and events for the community and visitors will also form part of the project, providing opportunities for users to engage with the heritage of the park.”

Anna Carragher, Chair of Heritage Lottery Fund Northern Ireland added, “This is such a special Park which has been used and loved by the local community for generations. We are delighted to be involved in breathing new life into the Park’s historic features, providing new and improved facilities and opportunities for everyone to learn more about its unique history.”


Photo: Left to right; Eddie Quinn, MD Quinn Automatic, Shirley Keenan, Project Development Officer, Newry, Mourne and Down District Council, Brian McCalmont, Old Warrenpoint Forum, Anna Carragher, Northern Ireland Chair Heritage Lottery Fund, Cllr Michael Carr, Deputy Chair Newry Mourne and Down District Council, Councillor William Clarke, Jim Boylan, Warrenpoint Heritage Development, Olga Fitzpatrick, Chairperson of Warrenpoint/Rostrevor Chamber of Commerce, Bill Reilly, Warrenpoint Heritage Development, Cllr Oksana McMahon and Shane Bonner, Engineer Quinn Automatic


Attachments:
warrenpoint_park_01.jpg
warrenpoint_park_01.jpg [ 162.95 KiB | Viewed 2087 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Fri Feb 09, 2018 10:09 am 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Children from St Dallans were given the opportunity to share their ideas for the future of their local park.

Quote:
Shirley Keenan (Newry, Mourne & Down District Council) visited our school today and met with a group of children to brainstorm and share ideas about what they would like to see in their local park. The children were first to see the council's plans and drawings as to what the newly improved park might look like.

The children loved sharing their input during this consultation session and Shirley was certainly impressed by some future 'Town Planners'.


http://www.stdallans.com/news/consultation-for-new-play-area-in-warrenpoint-municipal-park/656/
Source


Attachments:
std3.JPG
std3.JPG [ 142.72 KiB | Viewed 2086 times ]
std2.JPG
std2.JPG [ 136.42 KiB | Viewed 2086 times ]
stdallans.JPG
stdallans.JPG [ 150.65 KiB | Viewed 2086 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Fri Feb 09, 2018 10:39 am 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
For those interested, the submitted (passed) plans from 2015 are available here:

http://epicpublic.planningni.gov.uk/publicaccess/applicationDetails.do?activeTab=summary&keyVal=NTDNM8SV30000

For the less technically minded, the overall site plan and bandstand plans can be viewed from these links - there have been a few minor changes since then after consultations with heritage architects and horticulturists.

https://www.dropbox.com/s/3hwrdn8zjsz2tr4/submittedplans2015.jpg?dl=0

https://www.dropbox.com/s/86iyspfol3l9dsy/bandstand.jpg?dl=0


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Sun Feb 11, 2018 4:30 am 
Offline
Member
Member

Joined: Wed May 09, 2007 2:17 am
Posts: 962
Location: Frisco, Texas
Hey Brian, maybe the St. Dallan kids could give those "working" on the Bridge project a little help. Looks like they could use it.

Glad to see the park work is underway. Well done!

Pat


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Mon Feb 12, 2018 10:37 am 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
As I mentioned I have permission to enter the site and take photos as the work progresses. This will be on a weekly basis and supplemented by some photos taken by staff from the roof of the Whistledown hotel (the first 4 in this post)


Attachments:
Park (1).jpg
Park (1).jpg [ 303.47 KiB | Viewed 1984 times ]
Park (2).jpg
Park (2).jpg [ 190.33 KiB | Viewed 1984 times ]
Park (3).jpg
Park (3).jpg [ 1.43 MiB | Viewed 1984 times ]
Park (4).jpg
Park (4).jpg [ 1.41 MiB | Viewed 1984 times ]
_DSC7370.jpg
_DSC7370.jpg [ 257.82 KiB | Viewed 1984 times ]
_DSC7368.jpg
_DSC7368.jpg [ 262.98 KiB | Viewed 1984 times ]
_DSC7365.jpg
_DSC7365.jpg [ 385.13 KiB | Viewed 1984 times ]
_DSC7364.jpg
_DSC7364.jpg [ 418.95 KiB | Viewed 1984 times ]
_DSC7358.jpg
_DSC7358.jpg [ 435.32 KiB | Viewed 1984 times ]
_DSC7356.jpg
_DSC7356.jpg [ 258.31 KiB | Viewed 1984 times ]
_DSC7338.jpg
_DSC7338.jpg [ 343.55 KiB | Viewed 1984 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Mon Feb 12, 2018 11:40 am 
Offline
Member
Member
User avatar

Joined: Thu Feb 07, 2008 8:01 pm
Posts: 3225
Location: Ostrohe GERMANY
A few hours with a metal detector might turn up some old coins.


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Fri Feb 16, 2018 4:19 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
16-02-18


Attachments:
Park160218 (4).jpg
Park160218 (4).jpg [ 284.94 KiB | Viewed 1928 times ]
Park160218 (3).jpg
Park160218 (3).jpg [ 270.05 KiB | Viewed 1928 times ]
Park160218 (2).jpg
Park160218 (2).jpg [ 241.57 KiB | Viewed 1928 times ]
Park160218 (1).jpg
Park160218 (1).jpg [ 236.05 KiB | Viewed 1928 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Tue Feb 20, 2018 5:04 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Signs are now up showing the plans


Attachments:
plans.jpg
plans.jpg [ 326.49 KiB | Viewed 1833 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Wed Feb 28, 2018 12:14 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Photo from the Whistledown.


Attachments:
Park snow.jpg
Park snow.jpg [ 86.62 KiB | Viewed 1732 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Wed Feb 28, 2018 3:30 pm 
Offline
Member
Member

Joined: Tue Nov 20, 2012 3:37 pm
Posts: 125
I wonder if the 'wee castle' in the flower beds was saved or will it be on the never-seen-again list too?


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Thu Mar 15, 2018 6:24 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
15-03-18


Attachments:
_DSC7962.jpg
_DSC7962.jpg [ 530.37 KiB | Viewed 1540 times ]
_DSC7958.jpg
_DSC7958.jpg [ 563.69 KiB | Viewed 1540 times ]
_DSC7954.jpg
_DSC7954.jpg [ 432.06 KiB | Viewed 1540 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Tue Mar 20, 2018 4:48 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Work continues apace, the bandstand is getting stripped down to bare metal (all the old rotten woodwork and corroded metal is being replaced and the roof restored) ground works for drainage and pathways plus cables and other associated works also continues.


Attachments:
_DSC8194.jpg
_DSC8194.jpg [ 772.98 KiB | Viewed 1448 times ]
_DSC8199.jpg
_DSC8199.jpg [ 720.36 KiB | Viewed 1448 times ]
_DSC8213.jpg
_DSC8213.jpg [ 524.89 KiB | Viewed 1448 times ]
_DSC8223.jpg
_DSC8223.jpg [ 683.39 KiB | Viewed 1448 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Thu Mar 22, 2018 10:24 am 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Many thanks to Gerard Loughran Managing Director of Ballinliss Forge who sent me these photos showing some of the bandstand metalwork under repair


Attachments:
File comment: Restoration under way
P1020847.jpg
P1020847.jpg [ 116.69 KiB | Viewed 1409 times ]
File comment: Edge panels repaired and ready for paint
P1020846.jpg
P1020846.jpg [ 125.65 KiB | Viewed 1409 times ]
File comment: This part has to be recast and welded into balustrade
P1020845.jpg
P1020845.jpg [ 73.02 KiB | Viewed 1409 times ]
File comment: Gate welded together and ready for prep before painting.
P1020844.jpg
P1020844.jpg [ 138.52 KiB | Viewed 1409 times ]
File comment: Gate Parts before repair
P1020842.jpg
P1020842.jpg [ 110.04 KiB | Viewed 1409 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Thu Mar 22, 2018 2:34 pm 
Offline
Member
Member
User avatar

Joined: Wed May 14, 2008 1:48 pm
Posts: 5182
Brian - a lot of work going into the
Park.

It will be nice to see it all finished.


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Wed Apr 04, 2018 6:58 am 
Offline
Member
Member
User avatar

Joined: Mon Feb 04, 2008 10:32 pm
Posts: 1366
Location: Warrenpoint
Great photos. My dad used to re-paint the bandstand about every three years and also the railings around the park between 1980 and 2001.


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Mon Apr 09, 2018 7:09 am 
Offline
Member
Member

Joined: Thu Dec 13, 2007 9:00 pm
Posts: 621
Great to see these, Brian.

I almost got trapped in the park on my way to work - must have been on the day the official photo was being taken! I spotted the gate was open and decided to take a short cut to work. It was only when someone shouted out to me that the park was closed that I realised. I must pay more attention to what is going on around me!


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Tue Apr 10, 2018 1:00 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Work continues - estimated completion date is looking like August, the bandstand is getting a complete new roof and paint scheme chosen from paint samples uncovered by heritage experts, and the glass doors are being reinstated, groundwork wise drainage channels have been added and power cables placed underground for the new lighting and the new edgings and paving work has started. Work will start soon on the new children's play area and multi use games court (tennis etc) pavilion (interpretive centre) and park keepers hut.


Attachments:
Park 10-04-18 (8).jpg
Park 10-04-18 (8).jpg [ 481.16 KiB | Viewed 986 times ]
Park 10-04-18 (7).jpg
Park 10-04-18 (7).jpg [ 714.83 KiB | Viewed 986 times ]
Park 10-04-18 (6).jpg
Park 10-04-18 (6).jpg [ 734.5 KiB | Viewed 986 times ]
Park 10-04-18 (5).jpg
Park 10-04-18 (5).jpg [ 724.66 KiB | Viewed 986 times ]
Park 10-04-18 (4).jpg
Park 10-04-18 (4).jpg [ 699.58 KiB | Viewed 986 times ]
Park 10-04-18 (3).jpg
Park 10-04-18 (3).jpg [ 488.27 KiB | Viewed 986 times ]
Park 10-04-18 (2).jpg
Park 10-04-18 (2).jpg [ 659.17 KiB | Viewed 986 times ]
Park 10-04-18 (1).jpg
Park 10-04-18 (1).jpg [ 584.97 KiB | Viewed 986 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Tue Apr 10, 2018 2:47 pm 
Offline
Member
Member
User avatar

Joined: Wed May 14, 2008 1:48 pm
Posts: 5182
Brian - a lot of work being done there.
The edging looks nice along the pathways.
It will be lovely whenever it is finished.


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Wed May 02, 2018 3:44 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
2nd May 2018


Attachments:
_DSC9039.jpg
_DSC9039.jpg [ 279.75 KiB | Viewed 673 times ]
_DSC9037.jpg
_DSC9037.jpg [ 259.08 KiB | Viewed 673 times ]
_DSC9025.jpg
_DSC9025.jpg [ 420.37 KiB | Viewed 673 times ]
_DSC9023.jpg
_DSC9023.jpg [ 349.29 KiB | Viewed 673 times ]
_DSC9016.jpg
_DSC9016.jpg [ 302.33 KiB | Viewed 673 times ]
_DSC9012.jpg
_DSC9012.jpg [ 321.68 KiB | Viewed 673 times ]
_DSC9011.jpg
_DSC9011.jpg [ 361.5 KiB | Viewed 673 times ]
_DSC9000.jpg
_DSC9000.jpg [ 311.04 KiB | Viewed 673 times ]
_DSC8999.jpg
_DSC8999.jpg [ 265.57 KiB | Viewed 673 times ]
Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Fri May 25, 2018 4:07 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
Image

Image

Image

Image

Image


Top
 Profile  
Reply with quote  
 Post subject: Re: The Park 2018
PostPosted: Fri Jun 08, 2018 3:29 pm 
Offline
Site Admin
Site Admin
User avatar

Joined: Sun May 06, 2007 2:30 pm
Posts: 10440
Location: Warrenpoint
8th June 2018

Image
Image
Image
Image
Image
Image
Image
Image
Image
Image
Image
Image
Image
Image
Image
Image
Image


Top
 Profile  
Reply with quote  
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 22 posts ] 

All times are UTC


Who is online

Users browsing this forum: No registered users and 1 guest


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Group